ESTEC/Contract No. 13561/99/NL/SB
Monthly Progress Report
SAAPS-MR-2-99
Period: 1999-04-24--05-24
Author: Lars Eliasson
We have continued to develop the computer resources that are being used for this project. The Lund Division has now a better conection to the university network in Sweden, SUNET. The computers have also been upgraded with new systems which enables more effi cient operation of Java programs. Time has also been spent on learning how to use Java in the best way for SAAPS. A new web-domain has been created for IRF-L (irfl.lu.se).
The list of minimum people to contact is being prepared and will be discussed during PM1.
The main activity has been work on WP110.
Contracts have been signed.
WP 110 URD for data base and data base tools
The preliminary URD for the data base and some comments on data base tools are briefly described in a seperate report:
http://durque.irf.se/~satanom/rep110/report_110.html
WP120 SRD for data base and data base tools
Start T0+6 according to the schedule
WP130 Development of data base and data base tools
Start T0+11 according to the schedule
WP140 Test and update data base
Start T0+15 according to the schedule
WP205 Prototype of Spacecraft Anomaly Analysis, SAA
The prototype was installed on the server in April 1999.
WP210 URD for SAA
Start T0+3 according to the schedule
WP220 SRD for SAA
Start T0+5 according to the schedule
WP230 Development of SAA
Start T0+11 according to the schedule
WP240 Testing and demonstration of SAA with new data
Start T0+17 according to the schedule
WP305 Prototype of Satellite Anomaly Index, SAI
The prototype was installed on the server in April 1999.
WP310 URD for SAI
Start T0+4 according to the schedule
WP320 SRD for SAI
Start T0+6 according to the schedule
WP330 Development of
Start T0+11 according to the schedule
WP340 Testing and demonstration of SAI
Start T0+19 according to the schedule
None
Minimum list of people to contact will be established.
The web-server will be running in Lund and some Java applications will be available. Database will be implemented on the server.
None
No Open
Advance payment invoice will be sent to ESTEC before 1 June.
PM1 will be held in Lund starting at 13.00 on 17 June, 1999. A 1.5 day meeting is anticipated.
Internal home page
SAAPS home page
Swedish Institute of Space Physics
PO Box 812
SE-981 28 Kiruna, Sweden
Phone | +46 980 790 00 |
Fax | +46 980 790 91 |
Internet: | http://www.irf.se/irfk.html |
Swedish Institute of Space Physics
Solar-Terrestrial Physics Division
Scheelevagen 17
SE-223 70 Lund, Sweden
Phone | +46 46 286 21 21 |
Fax | +46 46 12 98 79 |
Internet: | http://www.astro.lu.se/~henrik/ |