Swedish Institute of Space Physics, Kiruna Division

Plasma and Energetic Electron Environment and Effects Extension S/C Anomaly Analysis

ESTEC/Contract No. 13561/99/NL/SB

Monthly Progress Report

SAAPS-MR-1-99

Period: 1999-03-25--04-23

Author: Lars Eliasson

1. Progress status
After the kick-off work has been concentrated on prototypes of the Spacecraft Anomaly Analysis system and the Satellite Anomaly Index, WP205, WP305.
 
Servers in Lund and Kiruna are being prepared and some information on the project is now available on internet for internal and external access.
 
WP 110 URD for data base and data base tools
Start T0+1 according to the schedule
 
WP120 SRD for data base and data base tools
Start T0+6 according to the schedule
 
WP130 Development of data base and data base tools
Start T0+11 according to the schedule
 
WP140 Test and update data base
Start T0+15 according to the schedule
 
WP205 Prototype of Spacecraft Anomaly Analysis, SAA
The first prototype has been installed
http://durque.irf.se/satanom/analysis.pl
It is briefly described in a report
http://durque.irf.se/~satanom/rep205_305/report_205_305.html
 
WP210 URD for SAA
Start T0+3 according to the schedule
 
WP220 SRD for SAA
Start T0+5 according to the schedule
 
WP230 Development of SAA
Start T0+11 according to the schedule
 
WP240 Testing and demonstration of SAA with new data
Start T0+17 according to the schedule
 
WP305 Prototype of Satellite Anomaly Index, SAI
The first prototype has been developed and is installed
http://durque.irf.se/satanom/real_time_pred.pl
It is briefly described in a report
http://durque.irf.se/~satanom/rep205_305/report_205_305.html
 
WP310 URD for SAI
Start T0+4 according to the schedule
 
WP320 SRD for SAI
Start T0+6 according to the schedule
 
WP330 Development of
Start T0+11 according to the schedule
 
WP340 Testing and demonstration of SAI
Start T0+19 according to the schedule
 
2. Problem areas/reasons for slippages
None
 
3. Events anticipated to be accomplished during next reporting period
Minimum list of people to contact will be established
Contract signed
First prototype of data base will be ready at the end or shortly after the next report
 
4. Status report on all long lead or critical delivery items
None
 
5. Action items
No Open
 
6. Milestone payment status
N/A
 
7. Expected dates for major schedule items
PM1 will be held in Lund on June 17-18, 1999.