Swedish Institute of Space Physics, Kiruna Division
ESTEC/Contract No. 13561/99/NL/SB
Monthly Progress Report
SAAPS-MR-10-99/00
Period: 2000-01-01--01-31
Authors:
Lars Eliasson and Peter WintoftTwo of the technical notes (TN1 Database and database tools and TN3 Satellite anomaly prediction module) have been uppdated See http://www.irfl.lu.se/saaps/saapsin t/.
Java code has been written that implements feed-forward neural networks. See http://sol.irfl.lu.se/saaps/saa psint/doc/
A network for the prediction of daily anomaly Meteosat-3 data using sum Kp as input has been implemented in Java. See http://sol.irfl.lu.se/saaps/saa psint/doc/
The Java matrix package JAMA has been incorporated. See http://www.irfl.lu .se/saaps/saapsint/java_related.html
WP 110 URD for the database and database tools
The User Requirements Document for the database and database tools URD ver sion 1 of WP110 was delivered on 28 October 1999.
WP120 SRD for the database and database tools, DB&T
The Software Requirements Document SRD version 0.1 was delivered on 2 December 1999.
The technical note TN 1 (Database and database tools) version 0.2 was delivered on 31 January 2000. This note had previously the title Exploration of data.
WP130 Development of DB&T
Start T0+11 according to the schedule
WP140 Test and update of DB&T
Start T0+15 according to the schedule
WP205 Prototype of Satellite Anomaly Analysis Module, SAAM
A description can be found at: http://www.irfl. lu.se/saaps/saapsint/wp205/wp205doc.html
WP210 URD for SAAM
The User Requirements Document for the Satellite Anomaly Analysis Module URD W P210 version 1.1 was delivered on 4 November 1999.
WP220 SRD for SAAM
The Software Requirements Document SRD version 0.1 was delivered on 2 December 1999.
A technical note TN 2 (Satellite anomaly analysis module) version 0.1 was delivered on 16 December 1999.
WP230 Development of SAAM
Start T0+11 according to the schedule
WP240 Testing and demonstration of SAAM with new data
Start T0+17 according to the schedule
WP305 Prototype of Satellite Anomaly Prediction Module, SAPM
The prototype was installed on the server in April 1999.
WP310 URD for SAPM
The User Requirements Document URD W P310 draft version 1 was delivered on 17 November 1999.
WP320 SRD for SAPM
The technical note TN 3 (Satellite anomaly prediction module) version 0.2 was delivered on 17 January 2000.
WP330 Development of SAPM
Start T0+11 according to the schedule
WP340 Testing and demonstration of SAPM
Start T0+19 according to the schedule
None
Updated versions of the SAAPS SRD will be delivered. Updated prototypes of satellite anomaly analysis and prediction modules (WP220 and WP320). Updated technical note (WP220)
None
The following 8 Action Items were defined during PM2 held in Kiruna 12-14 October:
1. Scheme for coding sensitive information shall be sent to Alain Hilgers for approval in the end of November 1999.**See page 10 in Database and database tool URD**
2. Alain Hilgers shall investigate the availability of other anomaly data sets at ESTEC. Information shall be sent to by end of October.
3. Peter Wintoft will send email remainder to those that have not responded and send the questionnaire to ESOC before the end of October. ** Letter and questions were sent by email on 16 November 1999**.
4. Alain Hilgers will give names to contact at ESOC before end of October.
5. Peter Wintoft shall send information and questionnaire to SWEN before end of October. ** A description of SAAPS was emailed to SWEN on 27 October 1999. **
6. Peter Wintoft shall investigate usefulness of environment data from polar orbits (at least DMSP and TIROS) before the end of November. ** Availability of DMSP data has been investigated. Decision to investigate other sources of LEO particle data. **
7. Peter Wintoft shall submit the URD for WP110 to Alain Hilgers before 31 October in pdf-format. Alain Hilgers shall notify in a couple of days if critical problems exist in the URD. **The URD was delivered on 28 October 1999. Response from Alain Hilgers was received on 5 November. **
8. A draft version of the URD for WP310 shall be sent to Alain Hilgers by mid-November. **Draft version was delivered on 17 November 1999. **
N/A
The mid-term review will be held at ESTEC on Monday 28 February, 2000.
Swedish Institute of Space Physics
PO Box 812
SE-981 28 Kiruna, Sweden
Phone |
+46 980 790 00 |
Fax |
+46 980 790 91 |
Internet: |
Swedish Institute of Space Physics
Solar-Terrestrial Physics Division
Scheelevagen 17
SE-223 70 Lund, Sweden
Phone |
+46 46 286 21 21 |
Fax |
+46 46 12 98 79 |
Internet: |