Open Data Interface, ODI
ESTEC/Contract No. 21964/08/NL/AT
Monthly Progress Report
ODI-MR-16-08/10
Period: 2010-01-01--01-31
Author: Lars Eliasson
1. Progress status
The ACE MFI 4-minute and ACE SWE 64-sec Level 2 solar wind data have been added. Code for downloading and parsing data have been added. The ACE MFI dataset covers the period 1997-09-02 to 2009-09-26 and contains 1 586 700 records. The ACE SWE extends over 1998-02-04 to 2009-08-30 with 5 705 111 records.
The "-zmode 2" option was added to the CDFExport command in generic.php. This will remove the dimensions of rVariables having a NOVARY variance.
A check for dimension variance have been added in odi.library.php. This is useful when multidimensional rVariables holding scalar data is imported. This check may be redundant with "-zmode 2" option above.
Ingestion of the Meteosat LR data; DH attached the skeleton and set files. The Meteosat anomaly data are in as well. Both are visible in SEDAT too.
Final (?!) cleanup of the IDL tools for SEDAT and the stand-alone read_odi.pro. DH added a subdirectory IDL under tools in the repository to hold this file. DH updated everything on spitfire, and checked that SEDAT is still working properly.
DH put together a cronjob file with all the live datasets we have so far. DH tested all the download scripts again, to have an idea how long they take to update datasets. At the same time, he also corrected the LF problems, so they work fine now on Linux. DH also re-ran populate on a number of datasets, everything works fine. The server should be very busy from now on!
DH has been in communication with Michael Liu of the cdf team on the distribution of the cdf toolkit for mingw and gfortran. He has prepared a new package.
Web page http://www.lund.irf.se/odi
WP 100 Core Database System
A draft of the ECSS-E40 documents (D1.2) is prepared including e.g. Software System Specification (version 0.1, dated 2008-11-14).
URD (D1.1) version 1.1 (2009-09-22).
User manual for the database administrator (D2) version 1.2 (2009-10-16).
Database system and source code (S1) rev 258 (2009-12-22).
The Users guide (D7) version 1.0 (2009-09-25).
WP200 Database
The structure of the database (S2) rev 258 (2009-12-22).
The Database Technical Note (D3) was updated to version 1.0 (2009-09-25).
WP300 SAAPS interface
Updated ECSS-E40 document at September 2009 according to the schedule
Software (S3) rev 258 (2009-12-22).
Technical note (D4a note D1 in SoW) version 1.0 has been written (2009-09-25).
WP400 SEDAT interface
Updated ECSS-E40 document at September 2009 according to the schedule
Software (S4) rev 258 (2009-12-22).
Technical note (D4b note D1 in SoW) version 1.0 has been written (2009-09-25).
WP500 SPENVIS interface
Updated ECSS-E40 document September 2009 according to the schedule
Software (S5) rev 258 (2009-12-22).
Technical note (D4c note D1 in SoW) version 1.0 has been written (2009-09-25).
WP600 Maintenance and support
Started October 2009.
WP700 Administration/management
Monthly progress reports
Final Report (D5, note D2 in SoW) ready in March 2010 according to the present schedule.
Abstract (D6, note D3 in SoW) ready in March 2010 according to the present schedule.
2. Problem areas/reasons for slippages
The date for delivery of software was delayed, partly due to part-time parental leave.
3. Events anticipated to be accomplished during next reporting period
No major.
4. Status report on all long lead or critical delivery items
None
5. Action items
The following action item was decided during the PM4:
Action Item PM-4 Hugh Evans shall discuss with the Contract Officer about the IPR procedure and initiate it
6. Milestone payment status
Progress payment has been received.
7. Expected dates for major schedule items
The maintenance phase will run until March 2010. Next meeting March 2010 at ESTEC.