Open Data Interface, ODI
ESTEC/Contract No. 21964/08/NL/AT
Monthly Progress Report
ODI-MR-14-08/09
Period: 2009-11-01--11-30
Author: Lars Eliasson
1. Progress status
A PM was held during the ESWW6 in Brugge, Belgium, on Tuesday 17 Nov. See minutes on http://www.lund.irf.se/odi/internal.
A poster presentation was given at the ESWW6. The presentation can be found on the ODI web page.
Several new datasets have been added and/or updated.
It was agreed that the IPR should be transferred to ESA. A header comment to be put into the source code was formulated.
DH added the AZUR and UARS datasets.
DH wrote a stand-alone IDL routine to read out data from ODI into a data structure defined by HE.
DH has defined a new set of entries for the spenvis.properties file to store the ODI database connection parameters. The main interface page for SPENVIS has been re-written to make use of these parameters and of the new php features being implemented in SPENVIS 4.7.
Web page http://www.lund.irf.se/odi
WP 100 Core Database System
A draft of the ECSS-E40 documents (D1.2) is prepared including e.g. Software System Specification (version 0.1, dated 2008-11-14).
The URD (D1.1) has been updated to version 1.1 (2009-09-22).
User manual for the database administrator (D2) was updated to version 1.2 (2009-10-16).
Database system and source code (S1) will be updated from version 0.91 in the beginning of December.
The Users guide (D7) was updated to version 1.0 (2009-09-25).
WP200 Database
The structure of the database (S2) will be updated from version 0.91 in the beginning of December.
The Database Technical Note (D3) was updated to version 1.0 (2009-09-25).
WP300 SAAPS interface
Updated ECSS-E40 document at September 2009 according to the schedule
Software (S3) will be updated from version 0.91 in the beginning of December.
Technical note (D4a note D1 in SoW) version 1.0 has been written (2009-09-25).
WP400 SEDAT interface
Updated ECSS-E40 document at September 2009 according to the schedule
Software (S4) will be updated from version 0.91 in the beginning of December.
Technical note (D4b note D1 in SoW) version 1.0 has been written (2009-09-25).
WP500 SPENVIS interface
Updated ECSS-E40 document September 2009 according to the schedule
Software (S5) will be updated from version 0.91 in the beginning of December.
Technical note (D4c note D1 in SoW) version 1.0 has been written (2009-09-25).
WP600 Maintenance and support
Start October 2009 according to the present schedule.
WP700 Administration/management
Monthly progress reports
Final Report (D5, note D2 in SoW) ready in March 2010 according to the present schedule.
Abstract (D6, note D3 in SoW) ready in March 2010 according to the present schedule.
2. Problem areas/reasons for slippages
The date for delivery of software was delayed, partly due to part-time parental leave.
3. Events anticipated to be accomplished during next reporting period
Software and documentation was delivered at the end of September.
4. Status report on all long lead or critical delivery items
None
5. Action items
The following action item was decided during the PM4:
Action Item PM-4 Hugh Evans shall discuss with the Contract Officer about the IPR procedure and initiate it
6. Milestone payment status
Progress payment invoice was sent September 2009 and payment has been received.
7. Expected dates for major schedule items
The maintenance phase will run until March 2010. Next meeting beginng of March at ESTEC.