Open Data Interface, ODI


ESTEC/Contract No. 21964/08/NL/AT

Monthly Progress Report

ODI-MR-7-08/09


Period: 2009-04-01--04-30

Author: Lars Eliasson


1. Progress status

Daniel Heynderickx and Peter Wintoft had a meeting on 1 April at Frascati, Italy in connection to the COST ES0803 meeting. Several items on the ODI database structure were tailored out.


The basic file structure of ODI was set up.


Continued development of the core ODI database with prototype code developed in SQL, PHP, and Unix scripts.


A collection of SQL tables to hold metadata were developed (metadata_tables_create.sql and metadata_tables_populate.sql).


The URD was updated and is now version 1.0.


Web page http://www.lund.irf.se/odi

WP 100 Core Database System

A draft of the ECSS-E40 documents (D1) is prepared including e.g. Software System Specification.

The URD version 1.0 has been written.

A draft of the Database Technical Note (D3) has been written.

User manual for the database administrator (D2) will be produced in May.

Database system and source code (S1) prototype is produced.

WP200 Database

Work with the populated database and source code. Prototypes have been generated for parts of the system.

MySQL database has been updated.

Update ECSS-E40 document.

The Database Technical Note first draft 0.1 was written in October and will be updated in May.


WP300 SAAPS interface

Updated ECSS-E40 document at T0 + 6 according to the schedule

The plan is that the software will be delivered on May 22nd

Technical note ready at T0 + 6 according to the schedule

WP400 SEDAT interface

Updated ECSS-E40 document at T0 + 6 according to the schedule

The plan is that the software will be delivered on May 22nd

Technical note ready at T0 + 6 according to the schedule

WP500 SPENVIS interface

Updated ECSS-E40 document at T0 + 6 according to the schedule

The plan is that the software will be delivered on May 22nd

Technical note ready at T0 + 6 according to the schedule

WP600 Maintenance and support

Start T0+6

WP700 Administration/management

Monthly progress reports

Final Report ready at T0 + 12

2. Problem areas/reasons for slippages

The date for the MTR has been slightly delayed.


3. Events anticipated to be accomplished during next reporting period

No major.


4. Status report on all long lead or critical delivery items

None

5. Action items

The following action item was decided during the PM1

Action Item PM-1 Hugh Evans shall investigate where the system will be hosted at ESTEC, allocate space, and arrange for the necessary licences and servers to be set up at ESTEC.


6. Milestone payment status

Progress payment expected after software delivery.


7. Expected dates for major schedule items

The second Progress Meeting (MTR) will take place 4 June, 2009 at ESTEC. Final delivery is November 2009 according to the present schedule. The agenda for the MTR meeting can be found on the internal pages http://www.lund.irf.se/odi/internal/.