Open Data Interface, ODI


ESTEC/Contract No. 21964/08/NL/AT

Monthly Progress Report

ODI-MR-3-08/09

Period: 2008-12-01--12-31

Author: Lars Eliasson


1. Progress status

Work has mainly been concentrated on the URD and system specification documents as well as the definition of metadata tables.


Web page http://www.lund.irf.se/odi

WP 100 Core Database System

A draft of the ECSS-E40 documents (D1) is prepared including e.g. Software System Specification and a URD.

A draft of the Database Technical Note (D3) has been written.

User manual for the database administrator (D2) will be produced.

Database system and source code (S1) prototype is produced.

WP200 Database

Work with the populated database and source code has started and prototypes have been generated for parts of the system.

MySQL database at T0 + 3.5 according to the schedule

Updated ECSS-E40 document at T0 + 3.5 according to the schedule

Updated Technical Note at T0 + 3.5 according to the schedule

WP300 SAAPS interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

WP400 SEDAT interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

WP500 SPENVIS interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

WP600 Maintenance and support

Start T0+6 according to the schedule

WP700 Administration/management

Monthly progress reports

Final Report ready at T0 + 12

2. Problem areas/reasons for slippages

None

3. Events anticipated to be accomplished during next reporting period

PDR teleconference will take place in January.


4. Status report on all long lead or critical delivery items

None

5. Action items

No open actions

6. Milestone payment status

Advance payment invoice was sent via EFIS during November.

7. Expected dates for major schedule items

Preliminary date for the first Progress Meeting is February 12, 2009 in Leuven. The PDR/IR teleconference is planned to take place 8 January 2008.