Open Data Interface, ODI
ESTEC/Contract No. 21964/08/NL/AT
Monthly Progress Report
ODI-MR-2-08/09
Period: 2008-11-01--11-30
Author: Lars Eliasson
1. Progress status
The ODI project was presented at the 5th ESWW in Brussels.
An informal meeting with participation from ESA, IRF, and DH Consultancy was held on November 19 during the ESWW. The ODI metadata were discussed and the relation to the PRBEM metadata.
The PRBEM metadata has been further analysed and tables have been created containing descriptions of the metadata. The tables will be used in the URD.
A draft of the URD has been created.
Contracts with ESA and the sub-contractor have been signed.
Web page http://www.lund.irf.se/odi
WP 100 Core Database System
MySQL database structure at T0 + 2 according to the schedule
Draft ECSS-E40 document at T0 + 2 according to the schedule
User manual for the database administrator at T0 + 2 according to the schedule
A draft of the Software System Specification has been created.
A draft of the Database Technical Note has been created.
WP200 Database
Start T0+2 according to the schedule
MySQL database at T0 + 3.5 according to the schedule
Updated ECSS-E40 document at T0 + 3.5 according to the schedule
Updated Technical Note at T0 + 3.5 according to the schedule
WP300 SAAPS interface
Start T0+3.5 according to the schedule
Updated ECSS-E40 document at T0 + 6 according to the schedule
Software package ready at T0 + 6 according to the schedule
Technical note ready at T0 + 6 according to the schedule
WP400 SEDAT interface
Start T0+3.5 according to the schedule
Updated ECSS-E40 document at T0 + 6 according to the schedule
Software package ready at T0 + 6 according to the schedule
Technical note ready at T0 + 6 according to the schedule
WP500 SPENVIS interface
Start T0+3.5 according to the schedule
Updated ECSS-E40 document at T0 + 6 according to the schedule
Software package ready at T0 + 6 according to the schedule
Technical note ready at T0 + 6 according to the schedule
WP600 Maintenance and support
Start T0+6 according to the schedule
WP700 Administration/management
Monthly progress reports
Final Report ready at T0 + 12
2. Problem areas/reasons for slippages
None
3. Events anticipated to be accomplished during next reporting period
No major event during December.
4. Status report on all long lead or critical delivery items
None
5. Action items
No open actions
6. Milestone payment status
Advance payment invoice was sent via EFIS during November.
7. Expected dates for major schedule items
Preliminary date for the first Progress Meeting is February 12, 2009 in Leuven. The PDR/IR teleconference is planned to take place 18 December 2008.