Open Data Interface, ODI


ESTEC/Contract No. 21964/08/NL/AT

Monthly Progress Report

ODI-MR-2-08/09


Period: 2008-11-01--11-30

Author: Lars Eliasson

1. Progress status

The ODI project was presented at the 5th ESWW in Brussels.


An informal meeting with participation from ESA, IRF, and DH Consultancy was held on November 19 during the ESWW. The ODI metadata were discussed and the relation to the PRBEM metadata.


The PRBEM metadata has been further analysed and tables have been created containing descriptions of the metadata. The tables will be used in the URD.


A draft of the URD has been created.


Contracts with ESA and the sub-contractor have been signed.


Web page http://www.lund.irf.se/odi

 

WP 100 Core Database System

MySQL database structure at T0 + 2 according to the schedule

Draft ECSS-E40 document at T0 + 2 according to the schedule

User manual for the database administrator at T0 + 2 according to the schedule

A draft of the Software System Specification has been created.

A draft of the Database Technical Note has been created.

 

WP200 Database

Start T0+2 according to the schedule

MySQL database at T0 + 3.5 according to the schedule

Updated ECSS-E40 document at T0 + 3.5 according to the schedule

Updated Technical Note at T0 + 3.5 according to the schedule

 

WP300 SAAPS interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP400 SEDAT interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP500 SPENVIS interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP600 Maintenance and support

Start T0+6 according to the schedule

 

WP700 Administration/management

Monthly progress reports

Final Report ready at T0 + 12

 

2. Problem areas/reasons for slippages

None

 

3. Events anticipated to be accomplished during next reporting period

No major event during December.

 

4. Status report on all long lead or critical delivery items

None

 

5. Action items

No open actions


6. Milestone payment status

Advance payment invoice was sent via EFIS during November.

 

7. Expected dates for major schedule items

Preliminary date for the first Progress Meeting is February 12, 2009 in Leuven. The PDR/IR teleconference is planned to take place 18 December 2008.