Open Data Interface, ODI
ESTEC/Contract No. 21964/08/NL/AT
Monthly Progress Report
ODI-MR-1-08/09
Period: 2008-10-20--10-31
Author: Lars Eliasson
1. Progress status
The kick-off meeting was held on 20 October 2008 as a teleconference. Participants were Annika Tenho (Estec), Hugh Evans (Estec), Lars Eliasson (IRF), and Peter Wintoft (IRF).
A web page has been set up with link to internal pages. Address: http://www.lund.irf.se/odi.
A software version control system has been set up (subversion).
Work on the identification of the ODI metadata has started. For this the metadata in SAAPS/SEDAT/SPENVIS/PRBEM has been studied.
Possible links with SEPEM has been discussed.
WP 100 Core Database System
MySQL database structure at T0 + 2 according to the schedule
Draft ECSS-E40 document at T0 + 2 according to the schedule
User manual for the database administrator at T0 + 2 according to the schedule
Draft Technical Note at T0 + 2 according to the schedule
WP200 Database
Start T0+2 according to the schedule
MySQL database at T0 + 3.5 according to the schedule
Updated ECSS-E40 document at T0 + 3.5 according to the schedule
Updated Technical Note at T0 + 3.5 according to the schedule
WP300 SAAPS interface
Start T0+3.5 according to the schedule
Updated ECSS-E40 document at T0 + 6 according to the schedule
Software package ready at T0 + 6 according to the schedule
Technical note ready at T0 + 6 according to the schedule
WP400 SEDAT interface
Start T0+3.5 according to the schedule
Updated ECSS-E40 document at T0 + 6 according to the schedule
Software package ready at T0 + 6 according to the schedule
Technical note ready at T0 + 6 according to the schedule
WP500 SPENVIS interface
Start T0+3.5 according to the schedule
Updated ECSS-E40 document at T0 + 6 according to the schedule
Software package ready at T0 + 6 according to the schedule
Technical note ready at T0 + 6 according to the schedule
WP600 Maintenance and support
Start T0+6 according to the schedule
WP700 Administration/management
Monthly progress reports
Final Report ready at T0 + 12
2. Problem areas/reasons for slippages
None
3. Events anticipated to be accomplished during next reporting period
No major event during November.
4. Status report on all long lead or critical delivery items
None
5. Action items
From Negotiation Meeting:
Action item 1: Peter Wintoft shall update Slide 5 of the presentation with the database tools as the interface between the SQL database and the SAAPS/SPENVIS/SEDAT tools.
Action item 2: Annika Tenho shall send a draft contract for approval to L. Eliasson after acceptance of the minutes from this meeting.
Both action are closed. Updated slide was sent 2008-10-20 and draft contract the same day.
6. Milestone payment status
Advance payment invoice will be sent via EFIS during November.
7. Expected dates for major schedule items
Preliminary date for the first Progress Meeting is January 15, 2009 in Leuven.