Open Data Interface, ODI


ESTEC/Contract No. 21964/08/NL/AT

Monthly Progress Report

ODI-MR-1-08/09


Period: 2008-10-20--10-31

Author: Lars Eliasson

1. Progress status

The kick-off meeting was held on 20 October 2008 as a teleconference. Participants were Annika Tenho (Estec), Hugh Evans (Estec), Lars Eliasson (IRF), and Peter Wintoft (IRF).


A web page has been set up with link to internal pages. Address: http://www.lund.irf.se/odi.


A software version control system has been set up (subversion).

Work on the identification of the ODI metadata has started. For this the metadata in SAAPS/SEDAT/SPENVIS/PRBEM has been studied.


Possible links with SEPEM has been discussed.

 

WP 100 Core Database System

MySQL database structure at T0 + 2 according to the schedule

Draft ECSS-E40 document at T0 + 2 according to the schedule

User manual for the database administrator at T0 + 2 according to the schedule

Draft Technical Note at T0 + 2 according to the schedule

 

WP200 Database

Start T0+2 according to the schedule

MySQL database at T0 + 3.5 according to the schedule

Updated ECSS-E40 document at T0 + 3.5 according to the schedule

Updated Technical Note at T0 + 3.5 according to the schedule

 

WP300 SAAPS interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP400 SEDAT interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP500 SPENVIS interface

Start T0+3.5 according to the schedule

Updated ECSS-E40 document at T0 + 6 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP600 Maintenance and support

Start T0+6 according to the schedule

 

WP700 Administration/management

Monthly progress reports

Final Report ready at T0 + 12

 

2. Problem areas/reasons for slippages

None

 

3. Events anticipated to be accomplished during next reporting period

No major event during November.

 

4. Status report on all long lead or critical delivery items

None

 

5. Action items

From Negotiation Meeting:

Action item 1: Peter Wintoft shall update Slide 5 of the presentation with the database tools as the interface between the SQL database and the SAAPS/SPENVIS/SEDAT tools.

Action item 2: Annika Tenho shall send a draft contract for approval to L. Eliasson after acceptance of the minutes from this meeting.


Both action are closed. Updated slide was sent 2008-10-20 and draft contract the same day.


6. Milestone payment status

Advance payment invoice will be sent via EFIS during November.

 

7. Expected dates for major schedule items

Preliminary date for the first Progress Meeting is January 15, 2009 in Leuven.