Monthly Progress Report
GIC-MR-4-03
Period: 2003-07-01-07-31
Author: Lars Eliasson
1. Progress
status
There has been very low activity during
this report period. The month of July is the main vacation period in Sweden.
Some of the personnel involved have participated in conferences of some
interest to the project.
The URD will be updated taken into account
the comments made during the meeting held in Lund in June and during internal
discussion within the project and with the sub-contractor. The draft URD was
planned to be re-submitted to ESTEC for comments during July 2003 but has been
slightly delayed. New estimated date of delivery is 22 August.
WP 100 User
requirements
Draft URD will be resubmitted to ESTEC for
comments August 2003.
ESTEC can comment on the first version but it
might be more efficient to wait until the second draft is
delivered.
Updated URD at T0 + 2 according to
the schedule
Final URD at T0 + 3 according to the
schedule
WP200 Database
Start T0+3 according to the
schedule
Technical note at T0 + 6 according to the
schedule
WP201 Solar wind and GIC
datasets
Start T0+3 according to the
schedule
Data set with GIC data ready at T0 + 4.5
according to the schedule
WP202 Dataset with computed geomagnetic data
in a dense grid
Start T0+3 according to the
schedule
Data set with geomagnetic data grid ready at T0
+ 4.5 according to the schedule
WP300 Model for computation of GIC from
geomagnetic field
Start T0+3 according to the
schedule
Software package ready at T0 + 6 according to
the schedule
Technical note ready at T0 + 6 according to the
schedule
WP301 Model for computation of geoelectric
field from geomagnetic field
Start T0+3 according to the
schedule
Software package ready at T0 + 5.5 according to
the schedule
WP302 Model for computation of GIC from
geoelectric field
Start T0+3 according to the
schedule
Software package ready at T0 + 5.5 according to
the schedule
WP400 Forecasting model of GIC from solar
wind data
Start T0+5 according to the
schedule
Software package ready at T0 + 9 according to
the schedule
Technical note ready at T0 + 9 according to the
schedule
WP401 Forecasting model of geomagnetical
grid from solar wind data
Start T0+5 according to the
schedule
Software package ready at T0 + 8.5 according to
the schedule
WP402 Forecasting model of observed GIC from
solar wind
Start T0+5 according to the
schedule
Software package ready at T0 + 8.5 according to
the schedule
WP500 Service
implemention
Start T0+3 according to the
schedule
Software requirements document ready at T0 + 12
according to the schedule
Prototype software system ready at T0 + 12
according to the schedule
System manual ready at T0 + 12 according to the
schedule
User manual ready at T0 + 12 according to the
schedule
Test report ready at T0 + 12 according to the
schedule
WP600 Cost-benefit
analysis
Start T0+12 according to the
schedule
Cost benefit report ready at T0 +
24
WP700 Management
Buisiness plan ready at T0 +
24
2. Problem areas/reasons
for slippages
None
3. Events anticipated to be
accomplished during next reporting period
Second version of draft URD sent to ESTEC for
comments.
4. Status report on all
long lead or critical delivery items
None
5. Action
items
No Open
6. Milestone
payment status
Advance payment has been
received.
7. Expected dates for major
schedule items
Date for the second Progress Meeting is during
the workshop at ESTEC 3-6 November 2003.