ESTEC/Contract No.
16953/02/NL/LvH
Monthly Progress Report
GIC-MR-2-03
Period: 2003-05-01-05-31
Author: Lars Eliasson
1. Progress
status
Work with the draft URD has continued together
with the subcontractor, FMI. The URD will be sent to ESTEC for comments in the
beginning of June.
The need for a new magnetometer was
discussed during
a meeting with (OKG/ELFORSK). The team has investigated this further. The
coverage in the south of Sweden should be increased to give better predictions.
A place and financing has been identified. The type of magnetometer
that is found
to be most suitable is also used by FMI.
WP 100 User
requirements
Draft URD will be delivered to ESTEC for
comments June 2003.
Updated URD at T0 + 2 according to
the schedule
Final URD at T0 + 3 according to the
schedule
WP200 Database
Start T0+3 according to the
schedule
Technical note at T0 + 6 according to the
schedule
WP201 Solar wind and GIC
datasets
Start T0+3 according to the
schedule
Data set with GIC data ready at T0 + 4.5
according to the schedule
WP202 Dataset with computed geomagnetic data
in a dense grid
Start T0+3 according to the
schedule
Data set with geomagnetic data grid ready at T0
+ 4.5 according to the schedule
WP300 Model for computation of GIC from
geomagnetic field
Start T0+3 according to the
schedule
Software package ready at T0 + 6 according to
the schedule
Technical note ready at T0 + 6 according to the
schedule
WP301 Model for computation of geoelectric
field from geomagnetic field
Start T0+3 according to the
schedule
Software package ready at T0 + 5.5 according to
the schedule
WP302 Model for computation of GIC from
geoelectric field
Start T0+3 according to the
schedule
Software package ready at T0 + 5.5 according to
the schedule
WP400 Forecasting model of GIC from solar
wind data
Start T0+5 according to the
schedule
Software package ready at T0 + 9 according to
the schedule
Technical note ready at T0 + 9 according to the
schedule
WP401 Forecasting model of geomagnetical
grid from solar wind data
Start T0+5 according to the
schedule
Software package ready at T0 + 8.5 according to
the schedule
WP402 Forecasting model of observed GIC from
solar wind
Start T0+5 according to the
schedule
Software package ready at T0 + 8.5 according to
the schedule
WP500 Service
implemention
Start T0+3 according to the
schedule
Software requirements document ready at T0 + 12
according to the schedule
Prototype software system ready at T0 + 12
according to the schedule
System manual ready at T0 + 12 according to the
schedule
User manual ready at T0 + 12 according to the
schedule
Test report ready at T0 + 12 according to the
schedule
WP600 Cost-benefit
analysis
Start T0+12 according to the
schedule
Cost benefit report ready at T0 +
24
WP700 Management
Buisiness plan ready at T0 +
24
2. Problem areas/reasons
for slippages
None
3. Events anticipated to be
accomplished during next reporting period
URD shall be finalised at the end of
June.
4. Status report
on all long
lead or critical delivery items
None
5. Action
items
No Open
6. Milestone
payment status
Advance payment invoice has been sent
to ESTEC.
7. Expected dates for major
schedule items
Date for the first Progress Meeting is June 18,
2003 in Lund.