Monthly Progress Report

GIC-MR-2-03

Period: 2003-05-01-05-31

Author: Lars Eliasson

1. Progress status

Work with the draft URD has continued together with the subcontractor, FMI. The URD will be sent to ESTEC for comments in the beginning of June.

 

The need for a new magnetometer was discussed during a meeting with (OKG/ELFORSK). The team has investigated this further. The coverage in the south of Sweden should be increased to give better predictions. A place and financing has been identified. The type of magnetometer that is found to be most suitable is also used by FMI.

 

WP 100 User requirements

Draft URD will be delivered to ESTEC for comments June 2003.

Updated URD at T0 + 2 according to the schedule

Final URD at T0 + 3 according to the schedule

 

WP200 Database

Start T0+3 according to the schedule

Technical note at T0 + 6 according to the schedule

 

WP201 Solar wind and GIC datasets

Start T0+3 according to the schedule

Data set with GIC data ready at T0 + 4.5 according to the schedule

 

WP202 Dataset with computed geomagnetic data in a dense grid

Start T0+3 according to the schedule

Data set with geomagnetic data grid ready at T0 + 4.5 according to the schedule

 

WP300 Model for computation of GIC from geomagnetic field

Start T0+3 according to the schedule

Software package ready at T0 + 6 according to the schedule

Technical note ready at T0 + 6 according to the schedule

 

WP301 Model for computation of geoelectric field from geomagnetic field

Start T0+3 according to the schedule

Software package ready at T0 + 5.5 according to the schedule

 

WP302 Model for computation of GIC from geoelectric field

Start T0+3 according to the schedule

Software package ready at T0 + 5.5 according to the schedule

 

WP400 Forecasting model of GIC from solar wind data

Start T0+5 according to the schedule

Software package ready at T0 + 9 according to the schedule

Technical note ready at T0 + 9 according to the schedule

 

WP401 Forecasting model of geomagnetical grid from solar wind data

Start T0+5 according to the schedule

Software package ready at T0 + 8.5 according to the schedule

 

WP402 Forecasting model of observed GIC from solar wind

Start T0+5 according to the schedule

Software package ready at T0 + 8.5 according to the schedule

 

WP500 Service implemention

Start T0+3 according to the schedule

Software requirements document ready at T0 + 12 according to the schedule

Prototype software system ready at T0 + 12 according to the schedule

System manual ready at T0 + 12 according to the schedule

User manual ready at T0 + 12 according to the schedule

Test report ready at T0 + 12 according to the schedule

 

WP600 Cost-benefit analysis

Start T0+12 according to the schedule

Cost benefit report ready at T0 + 24

 

WP700 Management

Buisiness plan ready at T0 + 24

 

2. Problem areas/reasons for slippages

None

 

3. Events anticipated to be accomplished during next reporting period

URD shall be finalised at the end of June.

 

4. Status report on all long lead or critical delivery items

None

 

5. Action items

No Open

 

6. Milestone payment status

Advance payment invoice has been sent to ESTEC.

 

7. Expected dates for major schedule items

Date for the first Progress Meeting is June 18, 2003 in Lund.

 